Recent Weekly Highlights

11/11/2024 through 11/29/2024


Site Activities as follows by Prime Contractor: Cianbro and Subcontractor: Ranger

  • Completed sidewalk placements for phase 1.
  • Placed the approach slab on the Waterville side.
  • Removed forms for the bridge deck.
  • Continued work on CMP duct bank.
  • Started installing forms for the curb.
  • Finished Water main installation on the Waterville side.

(MaineDOT Resident: Ben Walz )

  1. 1 IMG_0607
  2. 2 IMG_0689
  3. 3 IMG_0698

11/04/2024 through 11/08/2024


Site Activities as follows by Prime Contractor: Cianbro and Subcontractors: Suncoast reinforcing, And Ranger

  • Placed the last footing for abutment 2 wingwall for phase 1.
  • Continued working on sidewalk forms.
  • Continued watermain installation on the Waterville side.
  • Placed the 1st section of sidewalk for phase 1.
  • Started rebar installation for abutment 2 wingwall.
  • Re-installed the temporary ADA ramp for the pedestrian detour.

(MaineDOT Resident: Ben Walz )









10/21/2024 through 11/01/2024


Site Activities as follows by Prime Contractor: Cianbro and Subcontractors: Suncoast reinforcing, and Ranger

  • Completed the 2nd footing placement abutment 2 wingwall.
  • Started installing forms for the 3rd footing at abutment 2.
  • Continued sidewalk reinforcing bar installation and started installing forms.
  • Finished reinforcing bar installation for the Winslow and center span.
  • Completed the Winslow span and center span deck placement.
  • Began watermain installation (Waterville side)

(MaineDOT Resident: Ben Walz)











10/14/2024 through 10/18/2024


Site Activities as follows by Prime Contractor: Cianbro and Subcontractor: Suncoast reinforcing

  • Continued work installing forms for abutment 2 wingwall sub footing.
  • Continued reinforcing bar installation on the bridge deck.
  • Completed 1st concrete placement for the bridge deck.
  • Continued work on gantry foundations.


(MaineDOT Resident: Ben Walz )

  1. 1 IMG_0480
  2. 2 IMG_0546
  1. 1 IMG_0280
  2. 2 20241106_101743
  3. 3 IMG_0422
  1. 1 Screenshot 2024-10-25 120208
  2. 2 IMG_0203

09/23/2024 through 09/27/2024

Site Activities as follows by Prime Contractor: Cianbro and Subcontractor: Ranger

  • Continued installing forms for the bridge deck. 
  • Worked on demo at existing abutment 2. 
  • Installed CMP conduit and started installing forms for duct bank.
  • Continued work on the gantry foundations. 
  • Continued work on the watermain.

 

(MaineDOT Resident: Ben Walz)

  1. 1 Ticonic Bridge Project
  2. 2 Ticonic Bridge Project

09/16/2024 through 09/20/2024

Site Activities as follows by Prime Contractor: Cianbro and Subcontractor: Ranger

  • Placed the footing for gantry foundation D-2. 
  • Worked on installing the cofferdam for foundation E-2. 
  • Started installation of the watermain crossing the bridge. 
  • Worked on installing forms for the bridge deck. 
  • Excavated the area for CMP conduit installation. 

(MaineDOT Resident: Ben Walz)


  1. 1 Ticonic Bridge Project
  2. 2 Ticonic Bridge Project

09/09/2024 through 09/13/2024

Site Activities as follows by Prime Contractor

  • Started excavation behind abutment 2, removed approach slab and started wire cutting old backwall. 
  • Continued working on stage 2 gantry truss, Placed the seal for foundation D-2
  • Installed miradrain at abutment 1
  • Surveyed blocking points. 

(MaineDOT Resident: Ben Walz)


  1. 1 Ticonic Bridge Project
  2. 2 Ticonic Bridge Project
  3. 3 Ticonic Bridge Project

09/02/2024 through 09/06/2024

Site Activities as follows by Prime Contractor

  • Continued steel erection for phase 1. 
  • Placed concrete for abutment 2 backwall. 
  • Resumed work on gantry foundations for phase 2 truss, installing cofferdam for foundation D-2.

(MaineDOT Resident: Ben Walz)

  1. 1 Ticonic Bridge Project
  2. 2 Ticonic Bridge Project
  3. 3 Ticonic Bridge Project

08/05/2024 through 08/09/2024

Site Activities as follows by Prime Contractor: Cianbro and subcontractor: L & D Safety Marking

  • Continued wet cure on abutment 2 pedestals. 
  • Continued installing the backwall forms on abutment 1. 
  • Continued Steel erection, and bolt torquing. 
  • Re-applied the temporary pavement markings at Winslow intersection. 
  • Placed concrete for gantry foundation C-2, and continued work on foundation G-2. 

(MaineDOT Resident: Ben Walz)

  1. 1 Ticonic Street Project
  2. 2 Ticonic Street Project
  3. 3 Ticonic Street Project