5/18/2024 through 5/23/2024
Site Activities as follows by Prime Contractor: Cianbro, Subcontractor: General Concrete Cutting
- Completed Phase 1 deck removal.
- Continued structural steel removal – removing span 4 girders.
- Completed rebar and form installation and placed 2nd lift of Phase 1 of the pier.
- Continued abutment 1 demo and structural earth excavation.
(MaineDOT Resident: Ben Walz)